March 15 2018

From MakeICT Wiki
Jump to navigationJump to search
  • Board Members
    • President - Kim Burton
    • Vice President - James Lancaster - Late
    • Treasurer - David Springs
    • Secretary - Rustin Atkeisson
    • At Large Director - LaDeana Dockery
    • At Large Director - Kip Landwehr - Absent
    • At Large Director - Malissa Long - Absent
    • At Large Director - Kez Cook
    • Immediate Past President - Logan Pajunen -Absent
  • Members

Simon McHugh Thomas Bloom Nick Endicott Jeremiah Burian Mike Barushok Ken Steadman Jeff Eck Christian Kindel Ken Jaggard

  • Youtube Visitor - Ken Jaggard
    • will be talking to members
    • ask about history
    • is checking out makerspaces across the
  • Safety - Mike Barushok
    • SAFETY IS NUMBER ONE PRIORITY
    • Had a few issues
      • Need electrical drops to replace extension cords
      • A lot of trip hazards and aisle widths
      • Better Exit Signage
      • Need ways for emergency persons to make it thru the space
      • Need to keep 3 feet of clearance around electrical panels and gas appliances
      • Cleaning supplies are in an open area by the kids area
      • Should not have paper towels and toiletries near water heater
    • Will let fire marshal come to us but will correct what we can
    • Had member volunteer to help with redoing electrical
    • Kim B - Common workspace injuries
      • any slips/trips/falls?
        • lots of stuff on floors of studios
        • in front of laser cutter
        • front door
        • step to metal shop (grip tape has been added)
        • door out of classroom
        • print studio door
        • stuff in the hallway (growing collection of TVs)
          • Sedgewick county is doing an electronics waste collection
        • metal shop has slanted area in floor to garage door (most likely fix with paint outline)
      • muscle strains from heavy lifts
        • we have a dolly
        • pallet jack
        • lifting table
      • most common area for heavy lifts - plasma cutter area, but class encourages team lifts
    • falling objects
      • potential by back shelf (really tall)
      • metal rack may have some items that could fall
    • Repetitive motion injuries
      • potential in ceramics area
    • crashes/collisions
      • parking issues
      • lines have been redone
      • diagonal parking has been added to the south side of douglas
    • cuts and lacerations
      • light switch in jewelry (has been taped up)
      • need to make sure medical supplies are stocked up and easily found
      • need to make sure knives are sharp or replaced routinely
      • metal shop safety cabinet was recently restocked
      • metal shop does have a trauma kit, but may be moved soon
      • will require documentation handed to members as they are given keys
      • tours from Mike B. have been pointing out safety equipment
      • Ken B - other makerspaces require a safety video and an online test
      • Cutting wheel in metal shop wheel was a near miss situation
    • incident reporting
      • ex: guy caught his finger in the disc sander
        • member filled out an incident report
        • steps
    • exposure to toxic fumes
      • list of banned materials for laser cutter
      • woodshop laques proper ventilation for spray finishes
      • generally people spray paint outside of metal shop
        • there was discussion of adding a paint booth
      • ventilation fan was added to metal shop
    • what if member continues to do something unsafe
      • call security (can revoke key if need be)
      • people should be open and receptive to comments
    • Exposure to loud noises
      • metal shop/wood shop
        • grinders, air compressor
        • ear plugs are in grey cabinet
        • metal shop and wood shop both have their own safety glasses
        • PPE should be be highly visible and easily accessible
      • laser cutter/foam cutter? - need to measure with decimeter
    • human factor
      • complacency/fatigue/absent mindedness
      • chuck key was left in lathe/mill (not safe)
      • consumables on plasma cutter have been consumed ridiculously fast
      • should first few uses of equipement supervised?
      • should there be annual recertification? - maybe if class was free
        • most certification classes allow people to come back to be safe
        • maybe allow other people to show people how to run machines
          • have looked at using new members for volunteers
      • Ken - his space (50 member space) has a rule that if chuck key is left in machine, you lose use of that machine
        • all the machines have the manual next to the machine
        • suggest a buddy system for first use of machines
        • MakeICT does have the manuals on the wiki
          • a large number of members do not go to the wiki, still need something next to the machines
      • Children under 12 should be supervised in each area
    • Medical issues
      • need another 1st aid class
    • health/sanitation
      • got lax on food waste
        • need to always dispose of food trash in sealed container
      • if it’s too full, we need to take out the trash ourselves
        • need to either put a covered trash can next to popcorn machine or need to move popcorn machine next to kitchen area
        • still need to take care of lose popcorn around the makerspace
    • Mike says thank you


  • Bylaw change
    • proposign board terms changed from 1 year to every 2 yrs and stagger which positions are changed
      • half would be re-elected one year, the rest would be re-elected the next
    • Mike B - still have an issue with a learning curve
      • Mike B - harder to get people to commit to longer terms
      • Mike B - longer commitments are harder for people to see themselves in down the line
    • Kez C - we are past a point of ‘get it done’ attitudes and need the experience of a person willing to make the longer commitment.
    • Jeff E - would prefer to see positions staggered
    • Thomas B - would we do 1yr terms with 6 months election?
    • Kim B - that
would lead to an aggressive learning curve
    • Thomas B - if person wants to run for a consecutive term is rarely unopposed
    • David S - there will be unintended consequences
    • Nick E - 1yr term is not enough time to enact a plan
    • LaDeana D - 1yr is not long enough to really show ownership
    • Jeremiah B - There is a process already set for removing board members if need be
    • Mike B - last year election changed how bylaws are approved
    • James L - must have all members present
    • Thomas B - How long has this been on the forum?
    • Kim B - March 16
    • Jeremiah B - Directors at large need roles, nothing currently ties them to be involved with the space. There is a chance with 2 yr terms that someone that does not represent MakeICT is on the board for 6yrs. General membership may not be aware of what is going on.
    • Kim B - SHould we go forward with a survey/straw pole? Feels better with keeping bylaw on table for another 90 days


  • Bus
    • we have the title back!
    • Ken J - other spaces do have protocol for dead projects
      • can trash after 3 months
      • Dallas goes as far as to put stuff in storage units and charge for use
      • if it’s not labeled, it’s free game to anyone
      • if you let your membership lapse, your stuff is gone
      • still owned by the makerspace
      • could get rid of with 3 nerd rule?

Motion to adjurn - Kez 2nd - Jeff Eck